Today's visit - The crews have finished the roof work and are in the process of taking down the large scaffolding on the North side of the building.
On the upper concourse, all of the masonry block work is completed, work continues on finishing the restrooms and concession stands.
The Legacy Club is really coming along nicely, some new flooring has be installed as have some drink shelves.(a shelf to sit your drink on while standing there etc.)
The Krush club has the panels on the walls installed. Now they will be marked, removed and sent to the printing company, who will then add graphics to them.
The locker room area, the training room is getting concrete added today, most of the drywall is done . As for the locker rooms, the drywall is done, getting ready to install light fixtures and other things.
In the arena, the news speakers are being installed, they will hang from the ceiling in the corner areas above the court. They look just like the concert speakers that hang from the ceiling during shows.
The Hall of Fame room has the drywall done.
All of the other dressing rooms down by the locker rooms were gutted, they should start on them by the next visit.
Huff Hall update, the new seats have been installed in the balconies, no backs as of yet, I haven't been told anything on this project, so I can only tell what I see. It also looks like some new ADA seating is being installed up there, not sure where the elevator will be located to access this area.
Thanks for the update. Are all the various projects still on schedule?