Today's visit
In the arena work continues up on the ring, prepping it for all of the new lights, wire-ring, brackets etc. This will take awhile. The locker rooms have been completely demolished and they are now getting ready for new plumbing infrastructure, cutting the concrete floor etc.
The two new clubs are coming along, one has the drywall complete and was being painted today. The other one is getting drywall installed currently.
New flooring for the East entrance should begin next week, other area's TBD.
On the upper concourse all of the old glass has been removed and all of the new glass has been installed, adding the trim and sealants now.
The old wall on the upper concourse has now been completely removed, the only thing left are two old door frames from the NW and North entrances.
The two new restrooms are coming along, on one the walls are starting to be built. both are roughed in. Two area's have been built of cinder blocks (rooms), not sure what they will be used for at this time.
Everything is moving along fine with no worries about hitting their deadline. I'll head back in a couple more weeks.
As for photo's, they are in the system and out of my hands, they hope to have some up soon.